Abstrak

Project Management has been an important part of software development projects, therefore the use of technology to endorse effectiveness and efficiency of Project Management is a crucial aspect. PT. Trend Communications Internation (TRENDcom) is a company providing Project Management Office (PMO) service. Their main service is to provide expertise in managing Information Technology projects. One of the big issues they are facing is managing timeline. Late of delivery is caused by people, process and technology reasons. Technology-wise, the absence of application to let project manager and his PMO team the important activities that will cause delay on overall progress as well as the lack of reminder for their due project activities. Using Critical Path Method, an application is developed to address the issues. The application managed to give information of activities in a schedule which has big impact on overall delivery timeline and to provide reminder of due activities.

Author Biographies

Nurvelly Rosanti, Universitas Muhammadiyah Jakarta

Departemen Teknik Informatika

Fakultas TeknikErwin Setiawan, Universitas Muhammadiyah Jakarta

Departemen Teknik Informatika

Fakultas TeknikAsti Ayuningtyas, Universitas Muhammadiyah Jakarta

Departemen Teknik Informatika

Fakultas Teknik

References

Project Management Institute. 2009. Project Management Body of Knowledge (4th Edition). Project Management Institute. Pennsylvania,

USA.

Mosaic Project Services. 2007. The Origins of Modern Project Management. Mosaic Project

Services. Melbourne.

Baker, Samuel L. 2004. Critical Path Method (CPM). (http://hspm.sph.sc.edu/COURSES/J716/CPM/CPM.html, diakses 14 Desember 2014).

De Weck, Olivier. 2012. Critical Path Method (CPM) (ocw.mit.edu/…/MITESD_36F12_Lec02.pdf, diakses 14 Desember 2014).

Sommerville, Ian. 2011. Software Engineering (9th Edition). Pearson. Boston, Massachusettes, USA.

Solichin, Achmad. 2009. Pemrograman Web dengan PHP dan MySQL.

Full PDF : https://journal.uhamka.ac.id/index.php/teknoka/article/view/339/pdf

This web supported by : www.uhamka.ac.id

Leave a Reply

Your email address will not be published. Required fields are marked *